Sewerage levels of service
Activity: Pre- planning application
Action: Acknowledgement of receipt & application completeness
Level of service timetable: Review application within 7 days of receipt to ensure all relevant details are included or request additional information. Full response within 21 days of receipt
Activity: Pre - design application
Action: Review application
Level of service timetable: Review application and respond within 14 days
Activity: S104 application
Action: Acknowledgement of receipt & application completeness
Level of service timetable: Review application within 7 days of receipt to ensure all relevant details are included or request additional information
Activity: Full design review and response
Action: Review design Step 1
Level of service timetable: Full design review and respond within 28 days of receipt of application (this includes the 7 days to acknowledge and review the application)
Activity: Design acceptance
Action: Review design Step 2
Level of service timetable: Issue formal technical acceptance of submission - a further 14 days from receipt of additional information
Activity: Execute adoption agreement
Action: Update draft agreement
Level of service timetable: Issue draft agreement to customer for signing, 14 days after receipt of of inspection fees, coloured plans and all required legal & land matter details
Activity: Customer notifies of construction start date and requests inspections
Action: Inspections and construction period
Level of service timetable: Plan start up meeting and inspection regime. 1st inspection undertaken within 14 days of request
Activity: Construction complete
Action: Request for pre maintenance inspections
Level of service timetable: Inspections undertaken within 14 days from receipt of request
Activity: Issue pre - maintenance certificate/provisional certificate
Action: Construction is substantially complete
Level of service timetable: 7 days from confirmation that all construction works are satisfactory and receipt of as built and CCTV survey
Activity: Issue vesting certificate
Action: Vest sewers
Level of service timetable: Within 7 days on confirmation that construction is complete and all legal and land matters are complete