Activity: Pre- planning application
Action: Acknowledgement of receipt & application completeness
Level of service timetable: Review application within 7 days of receipt to ensure all relevant details are included or request additional information. Full response within 21 days of receipt

Activity: Pre - design application
Action: Review application
Level of service timetable: Review application and respond within 14 days

Activity: S104 application
Action: Acknowledgement of receipt & application completeness
Level of service timetable: Review application within 7 days of receipt to ensure all relevant details are included or request additional information

Action: 

Acknowledgement of receipt & application completeness

Level of service timetable: 

Review application within 7 days of receipt to ensure all relevant details are included or request additional information. Full response within 21 days of receipt

Action: 

Acknowledgement of receipt & application completeness

Level of service timetable: 

Review application within 7 days of receipt to ensure all relevant details are included or request additional information. Full response within 21 days of receipt

Action: 

Acknowledgement of receipt & application completeness

Level of service timetable: 

Review application within 7 days of receipt to ensure all relevant details are included or request additional information. Full response within 21 days of receipt

Levels of service

Sewerage